How to Install a Macerator Pump (General Installation Guide)
Important: All macerator pumps must be installed by a qualified plumber or engineer to comply with UK building regulations, electrical safety rules, and warranty conditions.
This is a general overview, not a technical installation manual.
1. Position the Macerator
-
Place the macerator directly behind the toilet or as close as possible to the waste outlet.
-
Ensure you have enough clearance behind the WC pan for the macerator inlet and connections.
2. Connect the WC Outlet to the Macerator
-
Fit the toilet’s horizontal outlet into the macerator inlet using the supplied connector or pan adaptor.
-
Ensure the seal is watertight and properly aligned.
3. Connect Additional Appliances (if required)
Many macerators allow extra inlets for:
-
Basin
-
Shower
-
Bath (model dependent)
-
Bidet
Use the side or top inlets according to the manufacturer’s instructions, ensuring correct fall on the gravity pipework.
4. Install the Discharge Pipework
-
Use the correct pipe size (commonly 22mm, 28mm, or 32mm).
-
Maintain a smooth run with minimal bends to maximise performance.
-
Incorporate a non-return valve if not already included.
5. Electrical Connection
-
Must be wired to a fused spur by a qualified electrician.
-
The macerator must not be connected to a standard plug socket in splash zones.
6. Test the System
-
Flush the toilet and run connected appliances.
-
Ensure the pump activates, runs, and stops correctly.
-
Check for leaks at all joints.
How to Install a Sewage Pumping Station (General Installation Guide)
Important: Installation of packaged pumping stations requires a qualified drainage engineer, as incorrect installation can cause flooding, electrical hazards, or system failure.
This overview provides the general process only.
1. Prepare the Excavation
-
Excavate a hole large enough for the chamber and concrete/aggregate surround.
-
Ensure depth allows correct inlet levels and final ground finish.
-
De-water the excavation if necessary.
2. Lower the Chamber Into Position
-
Carefully lower the chamber onto a prepared concrete base or level granular bed (depending on manufacturer requirements).
-
Ensure the chamber is perfectly vertical and stable.
3. Connect the Inlet Pipework
-
Bring the incoming sewer pipe into the chamber at the correct invert level.
-
Use the supplied rubber grommet or inlet seal.
-
Maintain the proper fall on the incoming pipe (typically 1:40–1:80).
4. Install and Secure the Pump(s)
-
Fit the submersible pump(s) onto the base or guide-rail system.
-
Attach the lifting chain if required.
-
Connect internal pipework and the non-return valve.
5. Install the Discharge Line
-
Connect the discharge pipe to the external rising main.
-
Include valves, bends, and fittings as specified.
-
Pressure-test where required.
6. Install the Control Equipment
-
Fit the float switches, level controls, or probes.
-
Mount any external control panel (for twin-pump systems or commercial units).
-
Ensure all electrical work follows UK wiring regulations.
7. Backfill the Excavation
-
Backfill around the chamber using concrete or suitable granular material as specified.
-
Backfill in layers to avoid distortion.
-
Do not overload the chamber before properly securing it.
8. Fit the Chamber Cover
-
Install the pedestrian- or vehicle-rated access cover.
-
Ensure the lid is level with the surrounding ground.
9. Commission the System
-
Fill the chamber with water.
-
Test automatic pump activation and shutoff.
-
Confirm correct flow, pump direction, and non-return valve operation.